LV Panel Changeover SOP
To safely transfer the load between two power sources (e.g., utility and DG/UPS) while maintaining continuity and protecting equipment and personnel.
2. Scope
Applicable to LV switchboards, distribution panels, and sub-panels in industrial, commercial, or institutional facilities.
3. Responsibilities
- Operators: Follow SOP, ensure safety, and maintain logs.
- Maintenance Team: Inspect and service changeover switches and panels.
- Supervisors: Authorize changeovers and monitor compliance.
4. Safety Precautions
- Only trained and authorized personnel may operate LV panels.
- Wear PPE: insulated gloves, helmet, and safety shoes.
- Confirm both sources are stable before changeover.
- Never operate panel with wet hands or in wet areas.
- Ensure proper earthing of panels and equipment.
- Keep clear of busbars and live connections during operation.
5. Pre-Operation Checks
- Visual Inspection:
- Check panel for damage, overheating, or loose connections.
- Ensure indicator lights and meters are working.
Source Verification:
- Confirm utility supply voltage and frequency are within limits.
- Verify generator or alternate source is available and running (if applicable).
- Load Assessment:
- Check total load and ensure it is within the panel capacity.
Isolation Readiness:
Isolation Readiness:
- Identify breaker positions for safe transfer.
- Ensure changeover switch is functioning properly.
6. Changeover Procedure
6.1 Manual Changeover
- Inform relevant personnel of upcoming transfer.
- Turn OFF the load breakers connected to the panel.
- Switch main source breaker OFF (e.g., utility).
- Operate the manual changeover switch to select the alternate source (e.g., generator).
- Close the main breaker for the alternate source.
- Turn load breakers ON sequentially.
- Verify correct voltage, current, and phase sequence at the panel.
- Record time, source, readings, and operator name in the logbook.
6.2 Automatic Changeover (ATS – Automatic Transfer Switch)
- Ensure ATS is functional and configured correctly.
- Check both sources for voltage and frequency limits.
- ATS will automatically detect utility failure and start generator if needed.
- Verify load is transferred smoothly and no breaker trips.
- Record changeover events and source readings in the logbook.
7. Monitoring During Operation
Continuously monitor:
- Panel voltage, current, and frequency
- Load distribution and balance
- Indicator lights and alarms
Ensure load remains within rated capacity.
8. Fault Handling
1).. No supply from alternate source:
- Check breaker positions and source availability.
- Inform control room and maintenance team.
2).. Panel breaker trips during changeover:
- Identify overloaded circuits.
- Reduce load or isolate faulty circuits before re-energizing.
3).. Phase reversal or incorrect voltage:
- Immediately disconnect load.
- Correct source or phase connection before re-energizing.
9. Shutdown / Reverting to Main Supply
- Turn OFF load breakers.
- Switch main source breaker ON (utility).
- Operate changeover switch back to main source.
- Close load breakers sequentially.
- Record readings and time in logbook.
10. Maintenance
- Monthly: Inspect panel, breakers, and changeover switch for signs of wear or overheating.
- Quarterly: Test ATS (if installed) and verify correct operation.
- Annually: Full preventive maintenance, including cleaning, tightening connections, and testing protection relays.
11. Documentation
- Logbook: Date, time, source, operator, readings, and observations.
- Fault report: Description and corrective actions.
- Maintenance record: Details of inspection, testing, and repairs.
12. Best Practices
- Never bypass interlocks or protective devices.
- Avoid frequent changeovers under full load.
- Ensure communication with control room during every changeover.
- Test alternate power source periodically under load conditions.

0 Comments